ARPA Maybole Pl and Riverhills Dr Storm Water Improvements (Temple Terrace, FL)

City of Temple Terrace | $1.2M | ARPA-Funded

2024-2025

  • Directed preconstruction coordination by resolving utility conflicts with TECO, Spectrum, and Frontier, ensuring seamless alignment before field mobilization for our client.

  • Led detailed quantity takeoff verification and subcontractor pricing analysis, aligning all pay items precisely with contract scope for our client.

  • Managed RFIs, utility adjustment plans, and subcontractor clarifications from pre-bid through construction, maintaining documentation accuracy and project continuity for the Prime Contractor