Water Treatment Plant Well Field Expansion (Palm Coast, FL)

City of Palm Coast | $946k

2025-2026

  • Installation of approximately 580 LF of 4-inch raw water main, directional drilling, valve installations, equipping two potable wells, and adding a permanent standby generator to improve system capacity and reliability.

  • Reviewed plans and specifications for compliance, prepared change orders, and obtained vendor quotes to ensure accurate pricing and scope control.

  • Performed site visits to track progress, verify completed work, identify issues/solutions, document status reports for compliance and payment verification.